Bellbridge Walking Trail
About the project
As part of the Our Bellbridge Masterplan we are sealing and extending the Bellbridge Walking Track.
Stage 1 of the project was completed in June 2023. In April 2024 we commenced works on the footpath starting at the park approximately 170 metres south-west of Mitta Avenue, Bellbridge and continuing to the Kurrajong Gap Boat Ramp (Victoria side Lake Hume Boat Ramp).
The project is currently expected to be completed in mid-2025.
Why is this project being undertaken?
The Bellbridge Our Town Place Plan identifies the need to enhance recreational and economic opportunities in the area. This project aligns with key economic development goals by:
- Boosting tourism: Enhancing the visitor experience along the Great River Road, making Bellbridge a more attractive stop for travellers.
- Encouraging community activation: Creating a welcoming space for residents to gather, relax, and enjoy the natural beauty of Lake Hume.
Project updates
June 2023
Stage 1 of the project is completed. Consultation for Stage 2 is scheduled for the near future.
April 2025
Works commenced on ANZAC Day to complete Stage 2 and 3, along with upgrades on Stage 1.
- Completion of Stage 2
- Completion of Stage 3
- Upgrades of Stage 1
The project is currently expected to be completed mid-2025.
June 2025
Stage 1 and 2 resurfacing works are nearing completion with Stage 3 set to commence shortly.
Stage 3 is the section connecting the Kurrajong Gap Boat Ramp (Victoria side of Lake Hume Boat Ramp) to the rest of the foreshore footpath.
November 2025
Council will be hosting an official opening of this project alongside the launch of the Bellbridge Container Cafe on December 7, 2025.